WIND FARM
Kiewit Power Construction Company contracted WB•Koester to assist in the construction of Rosewater Wind Farm in Reynolds, Indiana. The turbine foundations involved the excavation of 3,200 CY of soil. The concrete anchor foundation was formed within the excavation and roughly 750 CY of concrete was poured to for the anchor system. The key to this project success was the coordination and constant contact between WB•Koester and Kiewit.
Installed 25 wind turbine foundations
Excavated 140,000 CY of soils
Constructed 10 miles of access roads
Removed and replaced over 35,000 CY of topsoil